Case 3.2. Project not Acceptable after Configuration Changes
1 | Case description. |
2 | Recommended procedure |
Case Description
- The project is developed on a test bed and deployed in production.
- Requirements are revised.
- Change Management project management recommended procedure are followed to ensure all data is always on the Change Management server.
- Production starts.
- Problems are noted
Recommended Procedure
Important:
Make sure that all configuration applications are closed and remain closed through this process.
Procedure
- Stop the production project.
- Right-click Project in the Workbench.
- Select Manage>Show History on the Popup menu.
- Select the labeled version of the project that was running successfully
- Click Get to get that version
- Delete any files that were added from the local project.
- Modify any non-CIMPLICITY configuration changes that were made to support the requirements change.
Note: You may need to delete saved runtime information (e.g. SAVED_POINT files).
- Use project management best practices to ensure that the current version of the managed project matches the production system project.
- Start the production project.