Establishing Downtime Locations
A location must be selected to enable reasons. If a production unit has child units, any or all of the locations can selected. If a parent production unit has downtime, all child units also have downtime.
To establish downtime locations
-
In the Plant Applications Administrator, expand Plant Model.
-
Expand the department and production line that contains the desired production unit.
-
Right-click the production unit and select Configure Events on <production unit name>. The Event Configuration dialog box appears.
-
On the Configured Models tab, double-click on the downtime model to open the configuration screen.
-
Click the Reason Tree Configuration tab.
-
Select the Downtime Locations tab.
-
In the Downtime Locations dialog box, the selected Production Unit and its Child Units are displayed as potential locations for Downtime.
-
Select the location to be associated with the Downtime model. The Tree Selection dialog is displayed.
-
Select the desired Downtime tree for the location from the Tree Selection dialog, and click OK.
-
Save the model.
-
Close the Edit Model configuration screen, and reload services when prompted to incorporate the changes.