The initial schedule was for 35 days but was extended to 69 days due to the customer’s expanded work scope and the 14-day quarantine before the project commenced. Engineers from GE Vernova and FieldCore quickly implemented measures aiming to ensure the safe and steady operation of the outage and delivered more than one day ahead of schedule.
In Shenzhen, Guangdong Province, GE Vernova has the largest installed base for the 9E gas turbine in China. In April 2019, GE Vernova announced that it had successfully completed the world’s first installation of its DLN1.0+ with Ultra Low NOx combustion upgrade on nine GE Vernova 9E gas turbines at five power generation enterprises to help improve air quality and public health throughout China by reducing nitrogen oxide (NOx) emissions.